St George Hospital Redevelopment Project Stage 03

Kogarah, NSW

Project Overview

Absolute Fire Solution provided passive fire protection service as part of the St George Hospital Redevelopment Project – Stage 03.

St George Hospital Redevelopment Project Stage 03

CLIENT:

HVAC

LOCATION:

Kensington Street,
Kogarah NSW 2217

PROJECT DURATION:

12 months

SERVICES PROVIDED:

Provision of supply, installation, and certification services for electrical service penetrations, including fire damper inspections and independent third-party fire damper certification, carried out in accordance with applicable AS standards and NCC requirements to ensure installations achieve the required Fire Resistance Levels (FRLs).

Project Overview

Absolute Fire Solution provided passive fire protection service as part of the St George Hospital Redevelopment Project – Stage 03.

SCOPE OF WORK

  • Conducted a detailed review of builder drawings and fire-compartmentation layouts to establish the required FRLs for electrical service penetrations.
  • Prepared a comprehensive fire matrix specifying proposed passive fire protection systems, supported by relevant test reports, engineering assessments, and compliance documentation.
  • Provided ongoing technical support throughout the project, including participation in coordination meetings and timely responses to all passive fire protection enquiries.
  • Installed compliant fire protection systems for electrical and mechanical service penetrations in accordance with AS 1530.4 and AS 4072.1 to meet NCC performance requirements.
  • Inspected fire and smoke dampers in accordance with the relevant AS standards and NCC provisions, and issued a third-party independent Fire Damper Inspection Certificate accompanied by a detailed inspection register and report.
  • Compiled and submitted all certification deliverables, including Fire Seal and Smoke Seal Installation Certificates, Passive Fire Registers, photographic installation reports, and marked-up penetration drawings.